A new aerospace part comes in, the purchase order calls for a first article inspection, and the shop has to prove the very first part off the machine matches every line on the drawing. Done well, it is a one-time effort that protects the whole production run. Done badly, it turns into a late shipment, a rejected report, and a scramble to remeasure parts that already left the building.
This guide covers what a first article inspection is, when you need one, what goes into the report, and how to run the process in a working machine shop without stalling the job.
What Is a First Article Inspection?
A first article inspection, or FAI, is a full, documented check of the first part made by a new production process. Every characteristic on the drawing gets measured and recorded, along with proof that the right material, special processes, and specifications were used. The goal is to show that your process, not just one lucky part, can make the part to print.
It is different from a normal first piece check. A first piece check confirms a setup is right before a run starts, and it often covers only the critical features. A first article inspection covers everything on the drawing and becomes a formal record the customer can review.
In aerospace, the common reference is AS9102, which defines the forms and content for a first article inspection report. Many defense, medical, and commercial customers ask for something similar even when they do not name the standard.
When Is a First Article Inspection Required?
Your customer’s purchase order and quality clauses decide this, so read them first. The typical triggers are:
- A new part that you have never made for this customer.
- A design change, such as a new drawing revision that affects the part.
- A process change, such as a new machine, a new NC program, different tooling, or a move to another location.
- A change in source, such as a new material supplier or a new vendor for a special process.
- A lapse in production. AS9102 uses two years without making the part as a trigger.
- A customer request, often after a quality problem.
When only part of the design or process changed, AS9102 allows a partial FAI that covers just the affected characteristics. Ask the customer before assuming a partial is acceptable.
What Goes Into a First Article Inspection Report
AS9102 organizes the report into three forms. Even if your customer uses its own format, the same information is almost always expected.
- Part number accountability. The part number, revision, part name, serial number of the inspected part, and any subassemblies or detail parts included.
- Product accountability. Raw material, special processes such as heat treat, plating, or anodize, and functional testing, each with the specification and the certificate or supplier that backs it up.
- Characteristic accountability. Every design characteristic from the drawing, numbered to match a ballooned drawing, with the requirement, the actual measured result, and the gage or method used.
How to Run a First Article Inspection Step by Step
1. Review the requirements
Pull the purchase order, the drawing at the correct revision, and every specification called out on it. Note any customer forms, sample quantities, or source inspection requirements before the job starts, not after the parts are made.
2. Balloon the drawing
Number every characteristic on the drawing: dimensions, tolerances, notes, finish callouts, and general tolerances that apply. Each balloon becomes a line on the characteristic form. Missed balloons are one of the most common reasons a report gets rejected.
3. Collect material and process records
Gather the material certs for the lot you used and the certificates from each special process vendor. Check that the specifications on the certs match the drawing. If heat treat or plating is done outside, make sure the paperwork comes back with the parts.

4. Make the part with the production process
The first article has to come from the same machines, programs, tooling, and methods you will use for the production run. A part made on a different machine or with a hand-tuned program does not prove the process.
5. Measure every characteristic
Measure each ballooned feature and record the actual value, not just a pass or fail. Write down the gage used and confirm it is within calibration. If a customer or auditor later questions a result, the gage record is part of your answer.
6. Handle anything that fails
If a characteristic is out of tolerance, do not bury it. Write a nonconformance report, decide on the disposition, fix the cause, and rerun the inspection for the affected features. A clean record of how a problem was handled is far better than a report that looks perfect and is not.
7. Review, sign, and keep the record with the job
Have someone other than the person who measured the part review the report before it goes out. Sign it, send it to the customer, and file it with the job so the next person who makes the part can find it.

Common First Article Inspection Mistakes
- Using an old drawing revision or missing a note on the drawing.
- Recording pass or fail instead of actual measured values.
- Using a gage that is past its calibration date.
- Missing certs from an outside processing vendor.
- Keeping the report on paper in a binder, where nobody can find it when the part comes back two years later.
- Starting the production run before the first article is approved.
What to Look For in Inspection Software
Spreadsheets and paper forms can work for a single FAI, but they get hard to manage across many jobs and customers. When you look at software, ask:
- Can we build our own inspection forms, including first article, in-process, final, and nonconformance forms?
- Can forms capture measured values, pass or fail checks, photos, files, and signatures?
- Can a form be attached to the job, operation, or purchase order it belongs to?
- Can operators fill out forms at the machine instead of walking to the office?
- Is gage calibration history kept with the tools used for inspection?
- Are supplier certificates and material records tied to the same jobs?
How ShopXpert Supports First Article Inspection
ShopXpert has been building shop management software for machine shops since 2020, and inspection records live in the same system as jobs, suppliers, and tools. With ShopXpert quality and traceability, you can:
- Build your own forms. The drag-and-drop form builder creates first article inspections, in-process checks, final inspections, and nonconformance reports, with inspection checks, number fields, file uploads, signatures, tables, and dynamic tables.
- Attach forms to the work. Forms can be attached to the job, purchase order, or task they belong to, and assigned to the teams that fill them out.
- Fill them out at the machine. On the workstation, operators see the forms assigned to their job and department, fill them in, and save, without walking to the office.
- Trace the gages. Tools checked out of the vending system are linked to the employee and the job, and calibration history, intervals, certificates, and reminders live on each tool.
- Keep supplier records current. Supplier certificates are stored with expiry dates and alerts, and supplier forms can be assigned to purchase orders.
For aerospace work, ShopXpert for aerospace manufacturing shows First Article as its own job stage, so production can see what is waiting on inspection. Jobs and workstation queues run in production management, all on the same ShopXpert platform.
For the wider audit picture, read our guide to AS9100 traceability requirements. If special processes are part of your first articles, see how shops handle outside processing without losing the paperwork.
Make Your Next First Article the Easy Part
Bring a recent first article report, and we will show you how the same inspection would run in ShopXpert from the drawing to the signed record. Book a ShopXpert demo.